Quick answer
- Two documents are usually enough: proof of identity and proof of ownership or occupancy of the premises.
- Most DISCOMs accept applications online with a document upload.
- Legal limit: 7 days in metro cities, 15 days in other municipal areas, 30 days in rural areas (states may set shorter).
What documents do I need?
Under the Electricity (Rights of Consumers) Rules, 2020, an application needs proof of identity (Aadhaar, PAN, voter ID, passport or driving licence) and proof of ownership or occupancy (sale deed, property tax receipt, allotment letter, or a rent agreement with the owner’s consent).
Some DISCOMs also ask for a passport photo and a wiring test report from a licensed electrical contractor, so keep one ready.
How do I apply?
Most DISCOMs have an online form on their website or app. Choose the category (domestic), the load you need in kW and single or three phase, upload the documents and pay the charges online.
A team then inspects the site and installs the meter. You get a consumer number, which you will use for bills, complaints and schemes like rooftop solar.
How much does it cost?
Charges depend on your state and load: an application fee, a security deposit, and service line or development charges. For a typical small home the total is usually a few thousand rupees; larger loads and three-phase connections cost more.
The state tariff order or the DISCOM website lists the exact charges. Get a receipt for every payment.
How long does it take, and what if it is late?
The 2020 rules set maximum times: 7 days in metro cities, 15 days in other municipal areas and 30 days in rural areas, though hilly or remote areas may have longer limits. Many states have set shorter limits.
If the DISCOM misses the limit without a valid reason, complain in writing and escalate to the CGRF. Compensation for delays may apply as per your state regulator’s rules.
Frequently asked questions
Can a tenant get a new electricity connection?
Yes, with proof of occupancy such as a rent agreement, usually with the owner’s consent or no-objection.
How do I choose the right load in kW?
Add the wattage of appliances you may run together. A home with fans, lights, a fridge and one AC typically needs 3–5 kW; ask for three phase above about 5–7 kW or with several ACs.
How do I change the name on my electricity bill?
Apply to your DISCOM with proof of ownership, identity and, if needed, the previous owner’s NOC. Many DISCOMs allow it online.